Home / Tongariro Power Scheme maintenance resumes
Tongariro Power Scheme maintenance resumes
Submitted by Mike Birch on Tuesday, 25 March 2008 - 8:33am
in
Genesis Energy has advised that the Poutu Canal maintenance programme has been rescheduled for 25 March 2008 to 25 May 2008. The four month maintenance programme started last January, but was suspended due to electricity shortages and the need to maximise generation from the Tongariro Power Scheme. The Tongariro River below Poutu Intake (Access 10 run) will be flowing at about 30 to 35 cumecs, although rainfall and generation flow changes will affect flow rates. Check the Genesis Energy website for flow data.